2014 Field Projects Idaho 2014

Project Description

  • This project is a day-time paving job located at the main lane of US-95, 10 miles north of Coeur d’Alene, ID.
  • Paving Contractor: Interstate Asphalt and Concrete
Date:
Monday, May 5, 2014 – Thursday, May 8, 2014

Project Map

Important Notices

  • Roller shipping – deliver at US 95 N and Williams Lane. ETA: May 2-4, 2014.
  • Contractor Contacts: Pat Cove, Interstate Concrete & Asphalt, 208-755-9987, Pat.Cove@oldcastlematerials.com. Consultant: Elaine David, HDR, 208-859-0476, Elaine.Davis@hdrinc.com;
  • Staging area: US 95 SB near the jobsite
  • Machine Setup and Trial Runs: 2-5PM, May 4 (IC Vendors and FHWA IC team only)
  • Training for Roller Operators: 6AM, May 5
  • Onsite personnel – please bring a copy of the Field Summary Sheets

Open House

  • Date/Time: May 8th, 8AM to noon
  • Location: ITD, District 1 Office (600 W. Prairie Ave., Coeur d’Alene, Idaho 83815-8764)
  • Online registration webpage
  • Details and presentation files (coming up)

Weather Condition

wuLogoUrl

 

Click the WeatherUnderground icon for near term weather forecast. 

Material Types

Asphalt – Intermediate Course

Roller(s)

  • HAMM double drum IC roller
  • Sakai double drum IC roller
Other Testing Equipment
  • GPS (TopCon)
  • LWD-a (Lightweight deflectometer for asphalt) (Kessler)
  • Nuclear density gauge (ITD)

Objectives

  • Train contractors and DOT on intelligent compaction technologies
  • Study the relationship between IC and asphalt in-place densities

Meetings and Reports

Meetings
Documents

Contacts

  • DOT: Marvin Fenn, John Perfect (208-772-1224)
  • FHWA IC Team: Dr. George Chang (512-451-6233)
  • Paving Contractors: Pat Cove (208-755-9987); backup: Elaine Davis (208-859-0476)
  • Open House: John Perfect (208-772-1224)